Midelt I 632.9 MW Solar Storage Enters Detailed Design in Morocco

The short answer
Procurement notices confirm 1,432.9 MWc of PV and 2,524 MWh of storage for the Midelt program, with Midelt I entering detailed design. This transition signals active procurement for Africa's largest single-site solar-storage project, moving it from planning to execution.
Key facts
- Capacity
- 1,432.9 MWc PV and 2,524 MWh storage across three plants
- Stage
- Detailed design and procurement
- EPC or contractor
- China Energy Engineering for Midelt I; PowerChina for Midelt II and III
- Location
- Midelt, Morocco
- Owner or developer
- China Energy International
The construction period for Midelt I, the first facility in the Midelt solar program, is scheduled to run from January 15, 2027, to July 15, 2028, spanning exactly 18 months, according to procurement notices published in China between November 17 and 19 that Barlamane.com obtained. These documents specify a total capacity of 1,432.9 MWc of photovoltaic generation and 2,524 MWh of electrochemical storage across the three plants. They also outline the electrical architecture for Midelt II and III, including the allocation of various high-voltage equipment between the two sites.
These capacities, which are yet to be installed, align with the contractual and technical scopes submitted to suppliers by two distinct Chinese state-owned groups: China Energy Engineering Corporation for Midelt I, and PowerChina, through its East China Institute of Engineering, for Midelt II and III.
Midelt I integrates 632.9 MWc of photovoltaic capacity with 1,324 MWh of battery storage, equating to 2.1 MWh of storage per installed megawatt-peak. China Energy Engineering disclosed these figures in a notice regarding the procurement of air-insulated switchgear (AIS), noting that the values are slightly higher than the rounded estimates previously cited by the group, which had referenced a plant of approximately 630 MW paired with 1,300 MWh of storage.
A consortium comprising China Energy International, the Southwest Electric Power Design Institute, and China Energy Engineering Group signed the engineering, procurement, and construction contract for the facility on Thursday, August 27. The scope of work encompasses studies, design, equipment supply, construction, assembly, testing, and commissioning. China Energy described the development as the “largest solar-storage project on a single site in Africa.”
Two letters of intent were signed in June, one with Chinese manufacturer Longi Green Energy for photovoltaic modules and another with its compatriot Sungrow for the energy storage system. The reference capacities cited in these agreements (632.9 MWc and 1,324 MWh) align with the specifications detailed in the notice issued on November 18.
The procurement of AIS equipment encompasses the apparatus for an isolated air-insulated substation, including busbars, disconnection devices, sectionalizing mechanisms, measurement instruments, protection systems, and connection components, tailored to the selected configuration. This contract covers the hardware required to collect generated electricity, step up its voltage, and inject it into the grid, while solar panels and battery containers are addressed in separate lots.
China Energy International initiated a separate tender process on Thursday, November 19, for the study and design services for the Midelt I project. Acting as the buyer, the company designated the consortium responsible for the power plant as the end user. These two concurrent consultations—one for engineering and the other for electrical equipment—mark the project’s transition into the detailed design and procurement phase.
PowerChina equips Midelt II and III
Midelt II and Midelt III, which feature distinct architectural designs, collectively comprise 800 MWc of photovoltaic capacity and approximately 1.2 GWh of battery storage, with each site contributing 400 MWc and nearly 600 MWh, respectively. The two facilities will be situated on adjacent plots of land, located roughly 20 kilometers north of Midelt.
The scope of work assigned to PowerChina encompasses the full project lifecycle, including feasibility studies, procurement, construction, and commissioning. It also covers the 400 kV step-up substations, the infrastructure for power evacuation, the expansion of the substation at the far end of the transmission line, and two years of post-delivery maintenance. Equipment contracts will be executed in US dollars with HDEC Middle East Co DMCC, which is identified as the buyer in the tender notices.
The contract, published on Tuesday, November 17, covers the supply of 24 400 kV lightning arresters, with 12 units allocated to each central station. These devices are designed to shield the new 400/33 kV substations and their auxiliary systems from overvoltages resulting from lightning strikes or switching operations on the grid.
The contract covers design, manufacturing, testing, packaging, transport to the port of shipment, export formalities, factory plans, spare parts, special tools, and assembly assistance in Morocco. The equipment must be delivered free on board (FOB) at a Chinese port before September 15, 2027.
PowerChina has included this procurement in a broader purchasing package, which also includes two 400 kV SF6 gas-insulated circuit breakers, one for each plant, designed to interrupt normal or fault currents to isolate damaged equipment while preserving the rest of the grid. Their delivery is scheduled for the same deadline.
Two sets of disconnectors, one per plant, each combine two 420 kV devices with one 230 kV unit, totaling six components. Unlike circuit breakers, these are designed to create a visible and safe electrical separation during maintenance or operational work. They will be integrated into the 400/33 kV substations and delivered on the same schedule.
The receiving grid is also being adapted
Midelt III is also the subject of a separate contract for two 400 kV reactors intended for the substation located at the far end of the transmission line. These devices absorb a portion of the reactive power generated by long high-voltage links and keep voltage within its technical limits. Their inclusion confirms that the project extends beyond the plants and their internal substations to the receiving grid.
PowerChina opened another negotiation on Friday, November 13, for the main transformers of Midelt II and III. The selected supplier will also sign in dollars with HDEC Middle East.
A royal decree has authorized Masen Capital, the investment arm of Morocco’s Agency for Sustainable Energy (Masen), to acquire a 25% stake in the project companies for the Midelt II and Midelt III solar plants, as well as in the two entities responsible for their maintenance. The selected private partners will hold the remaining 75% equity in each facility. According to calculations by Barlamane.com based on procurement notices published in China, the existing Midelt I plant will contribute 44.2% of the complex’s total photovoltaic capacity but 52.5% of its battery storage. The new Midelt II and III installations will supply the remaining 55.8% of the solar capacity and 47.5% of the storage capacity.
Frequently asked questions
How much battery storage is allocated to Midelt I compared to the other two plants in the program?
Midelt I integrates 1,324 MWh of battery storage, which is 52.5% of the total. The remaining 47.5% is split between Midelt II and III, with each site contributing nearly 600 MWh.
Which Chinese state-owned groups are responsible for the EPC of the Midelt solar and storage facilities?
China Energy Engineering Corporation is handling Midelt I, while PowerChina is responsible for Midelt II and III. These assignments are detailed in the procurement notices published in China.