Vattenfall opens first hybrid park in Germany

Key facts
- Vattenfall opened the Hommerdingen-Biesdorf hybrid plant in Rhineland-Palatinate, Germany, combining wind and solar generation under one operational roof
- The project utilizes a single grid connection to Westnetz, treating the solar array technically as an additional wind turbine unit
- This is the first hybrid wind and solar power plant in Germany, replicating a concept Vattenfall has used in the Netherlands and Great Britain
Vattenfall has opened the Hommerdingen-Biesdorf hybrid power plant in the presence of Michael Ebling, Minister for Economic Affairs, Tourism, Energy, and Climate of the state of Rhineland-Palatinate. For the first time in Germany, the company is combining electricity generation from wind and solar power under one roof, thus implementing a concept that Vattenfall has been operating for several years in the Netherlands and Great Britain, among other places.
The Hommerdingen-Biesdorf hybrid power plant consists of four wind turbines with a combined rated output of 17 MW and more than 12 000 solar modules with a rated output of 7.6 MWp. It is located on the municipal boundaries of Hommerdingen (wind farm) and Biesdorf (solar), which belong to the Verbandsgemeinde Südeifel near the Luxembourg border.
With the Hommerdingen-Biesdorf project, Vattenfall is pursuing the approach of connecting the solar park and the wind farm to the distribution network of the regional operator Westnetz via a single grid connection. The solar park is technically treated like another wind turbine, so only one grid connection is needed for the entire facility. Westnetz has agreed to this innovative concept.
At the opening of the hybrid park, Rhineland-Palatinate’s Minister for Economic Affairs and Energy, Michael Ebling, commented: “The Hommerdingen-Biesdorf hybrid park is a flagship project for a smart, efficient, and economical energy transition. It demonstrates that wind and solar energy don’t have to compete for scarce grid capacity, but can complement each other effectively. The crucial factor is not just generating more renewable electricity, but also integrating it into our power grids as efficiently as possible. For such innovative solutions to become widespread, we need reliable framework conditions, fast permitting processes, and intelligent grid connection concepts. At the same time, the project shows how entrepreneurial courage, technological innovation, and local commitment can work together. Because the energy transition takes place locally – and people and communities should benefit from it through regional value creation. I hope this project will inspire many others in Rhineland-Palatinate.”
The complementary generation profiles of wind and solar power utilise the distribution grid more efficiently compared to either technology individually. This leads to better overall use of the existing grid infrastructure and reduces the risk of grid overload. Furthermore, grid connection costs are significantly lower compared to stand-alone systems.
Catrin Jung, Senior Vice President and Head of the Wind Business Unit at Vattenfall, added: “We are delighted to have now realised our first hybrid project in Germany. This is especially true because we were able to leverage our existing expertise from previous projects. The Hommerdingen-Biesdorf project demonstrates how the energy transition can succeed: through the intelligent combination of wind and solar power, the efficient use of existing infrastructure, and the close collaboration of many partners in the region. We intend to continue this success story and plan to supplement our renewable energy generation with storage in the future to make the renewable energy system even more flexible and robust.”
For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.
The Autumn issue of 2026 is available now! The new issue begins with a regional report on Asia Pacific, looking at the region’s transition from building capacity to building systems. The issue also explores topics such as offshore wind foundations, solar maintenance, training the new workforce, inspection & maintenance, and more! With insights from experts such as Everllence, BW Ideol, EM&I, Watson Farley & Williams, and many more, make sure to check out this issue now.
Pvola take
This development signals a shift toward integrated renewable assets that optimize grid access efficiency for developers. By consolidating wind and solar under a single connection point, the project reduces infrastructure costs and simplifies permitting complexities. Investors should note that such hybrid models can enhance project bankability by demonstrating operational synergy and local regulatory acceptance.
Frequently asked questions
What is the significance of the Hommerdingen-Biesdorf hybrid power plant for Vattenfall in Germany?
It is the first facility in Germany to combine wind and solar generation under one roof. Vattenfall has previously operated similar hybrid concepts in the Netherlands and Great Britain.
How does the Hommerdingen-Biesdorf project handle grid connection for its wind and solar assets?
The solar park is technically treated like another wind turbine, allowing the entire facility to use a single grid connection. This innovative approach was agreed upon by the regional network operator Westnetz.