PvolaSolar & Storage← All stories

Markets & Policy

India Opens Bids for 1,000 MW Standalone BESS in Andhra Pradesh

4 min read
India Opens Bids for 1,000 MW Standalone BESS in Andhra Pradesh

The short answer

APTRANSCO released a tender on November 19, 2026, for 1,000 MW/4,000 MWh of standalone BESS in Andhra Pradesh. The procurement is split into two 500 MW segments, one with VGF and one without, binding developers to a 12-month commissioning timeline.

Key facts

Jurisdiction
Andhra Pradesh, India
Instrument
Tariff-Based Competitive Bidding (TBCB)
Status
Tender released November 19, 2026
Scope
1,000 MW/4,000 MWh standalone BESS at designated substations
Rate or target
500 MW with VGF, 500 MW without VGF

[India's UPCL Invites Bids for 41 MW/102.5 MWh Standalone BESS]

Uttar Pradesh Power Corporation Limited (UPCL) released a tender on Nov 17, 2026, for 41 MW/102.5 MWh of grid-interactive standalone battery energy storage systems (BESS) to be installed at six 33/11 kV substations across Uttarakhand. The procurement will follow a build-own-operate model, with competitive bidding based on capacity charges. Individual project capacities will range from 4 MW/10 MWh to 10 MW/25 MWh, distributed across the districts of Uttarkashi, Haridwar, and Tehri. Land for the installations will be provided on a right-of-use basis.

The systems are required to complete two full charge-discharge cycles per day, with 2.5-hour discharge periods aligned to morning and evening peak demand. Central government viability gap funding (VGF) will provide a non-recurring grant of up to INR 1.8 million per MWh of eligible capital cost. Projects must be commissioned within 12 months of the later of either the effective date of the Battery Energy Storage Purchase Agreement (BESPA) or the handover of the land. The BESPA term is set at 12 years from the date of full commissioning. Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact:

For more information on how to access our research reports, please contact:

[Delhi Metro Invites Bids for ISTS-Connected Solar-Plus-BESS Project]

Delhi Metro Rail Corporation (DMRC) has issued an open invitation for bids under Contract Package ORE/01 to procure renewable energy from an Inter-State Transmission System (ISTS)-connected solar photovoltaic project featuring a co-located Battery Energy Storage System (BESS). The project developer will be selected through an e-reverse auction process. The successful bidder is required to complete the project within 15 months of the Letter of Award. The tender document fee is set at INR 20,000, excluding Goods and Services Tax (GST), while the Earnest Money Deposit (EMD) stands at INR 239 million (INR 23.9 crore). Online bid submission will commence on December 3, 2026, at 09:00 and conclude on December 10 at 15:00. Technical bids are scheduled to be opened on December 11 at 15:00. Dates for financial bid opening and the e-reverse auction will be communicated separately.

[APTRANSCO Invites Bids for 1,000 MW/4,000 MWh Standalone BESS in Andhra Pradesh]

The Transmission Corporation of Andhra Pradesh Limited (APTRANSCO) has issued a Phase-II tender for the 2026-27 fiscal year to procure 1,000 MW/4,000 MWh of standalone Battery Energy Storage Systems (BESS) at designated substations within Andhra Pradesh. The proposed projects will feature a four-hour duration and are to be developed under the Build-Own-Operate (BOO) model via Tariff-Based Competitive Bidding (TBCB). The total capacity is divided into two equal segments: 500 MW/2,000 MWh supported by Viability Gap Funding (VGF) through the Power System Development Fund (PSDF), and 500 MW/2,000 MWh without VGF assistance. The tender documentation was released on November 19, 2026. A pre-bid meeting is scheduled for December 2 at 11:00, with the bid submission deadline set for December 14 at 17:00. The bid opening is planned for December 17 at 11:00. The tender fee is set at INR 89,005. The specific order value is not disclosed, and details regarding the Earnest Money Deposit (EMD) as well as technical and financial qualification criteria must be verified in the official Request for Submission (RfS).

[APTRANSCO Launches 1,000 MW/4,000 MWh Standalone Battery Storage Tender]

APTRANSCO has issued a request for proposals for the development of 1,000 MW/4,000 MWh of standalone battery energy storage systems at designated substations across Andhra Pradesh. The project will be executed under a build-own-operate framework, utilizing a tariff-based competitive bidding process. The tender is divided into two distinct components, each with a capacity of 500 MW/2,000 MWh. One of these components is eligible for viability gap funding of up to INR 1.8 million/MWh from the Power System Development Fund, whereas the other component does not include VGF support. Bids are due by Dec. 14, 2026.

[ACME Commissions Two Rajasthan BESS Tranches Totaling 51.87 MW/218.323 MWh]

Pvola take

The split structure isolates the cost of grid support from the cost of energy arbitrage, forcing bidders to price VGF dependence explicitly. This transparency allows asset owners to model cash flows without assuming state subsidies, reducing the risk of underpricing in the non-VGF segment.

Frequently asked questions

What are the capacity and location details for UPCL's new standalone BESS tender in India?

UPCL is procuring 41 MW/102.5 MWh of standalone BESS for installation at six 33/11 kV substations in Uttarakhand. The project will be distributed across the districts of Uttarkashi, Haridwar, and Tehri under a build-own-operate model.

How does the viability gap funding apply to the UPCL BESS procurement in Uttarakhand?

The tender includes a non-recurring VGF grant of up to INR 1.8 million per MWh of eligible capital cost. This funding is intended to support the financial viability of the grid-interactive storage systems being procured.

What are the operational requirements and commissioning timeline for the UPCL BESS projects?

The systems must complete two full charge-discharge cycles daily with 2.5-hour discharge periods aligned to peak demand. Projects must be commissioned within 12 months of the later of the BESPA effective date or land handover.