Peru Delays Long-Term Solar Tenders in New Procurement Regulation

The short answer
Peru's Ministry of Energy and Mines will publish its electricity procurement regulation in November without reserving long-term tenders for new wind and solar projects. This omission forces developers to compete with operational thermal and hydro plants, threatening the financing of a 14.5 GW pipeline.
Key facts
- Jurisdiction
- Peru
- Instrument
- Regulation on Electricity Procurement for Regulated Users
- Status
- Publication announced for November
- Scope
- 14.5 GW solar pipeline and 1,200 MW installed capacity
- Rate or target
- 10-year tender program for regulated users
The long-awaited regulation intended to boost wind and solar power generation in Peru may face a new setback after the Ministry of Energy and Mines (MINEM) announced its publication in November without incorporating the request to reserve long-term tenders of up to 15 years for new projects.
The proposal from the Peruvian Society of Renewable Energies (SPR) aimed to prevent solar and wind projects under development from competing with already operational plants for the contracts required to secure bank financing.
New regulation could leave renewables without financial backing
At Expo Solar Perú 2026, Undersecretary of Electricity Luis Santillán stated that the Regulation on Electricity Procurement for the Supply of Regulated Users would include a 10-year tender program to facilitate investment financing.
According to MINEM figures, solar energy accounted for 4.3% of electricity generated in Peru between January and August 2026, and the country has already surpassed 1,200 MW of installed photovoltaic capacity.
Eleven additional solar projects planned for the Ica, Arequipa and Moquegua regions would add 2,000 MW of capacity, representing investments exceeding USD 1.7 billion, with commercial operation projected between 2026 and 2030.
Such expansion must be supported by energy storage, distributed generation and new transmission lines, the official noted. The Ministry of Energy and Mines (MINEM) estimates the country’s solar potential at 937 GW, although current utilization remains limited.
Infobae Perú learned that, despite these figures, the government’s final proposal would require renewable energy developers to compete against thermal and hydroelectric plants for contracts that offer greater market predictability.
According to the Peruvian Energy Regulatory Office (SPR), this mechanism could impact a pipeline of 67 solar projects under review, totaling 14.5 GW of capacity and an estimated investment of USD 10 billion, as some of these initiatives require long-term contracts to secure financing and proceed to construction.
SPR questions legacy plants competing in long-term markets
Juan Pedro Aramburú, president of the Peruvian Society of Renewable Energies (SPR), warned that opening long-term power purchase auctions to already operational plants could restrict the addition of new capacity to the grid.
He argued that the primary barrier for solar, wind, and battery projects is not technological but regulatory. Without contracts that guarantee future revenue streams, developers cannot secure the financing required to build these facilities.
Aramburú also countered the notion that renewables cannot provide firm power, explaining that when paired with battery storage, they can deliver reliable output. He noted that batteries can maintain power levels during generation dips for several hours and provide essential ancillary services to the grid.
However, he cautioned that Peru currently lacks a mechanism to compensate for these specific functions. “In Chile, more than 4 GW of batteries are already operating, with plans to build between 8 GW and 10 GW. That volume exceeds the maximum demand of the Peruvian system using batteries alone,” he stated.
The SPR president concluded that without new financeable contracts and payments for storage services, the system may continue to rely on diesel generators whenever available generation falls short.
The resource functions as a backup when other technologies fall short, potentially increasing marginal costs by up to tenfold. This surge impacts the pricing of contracts for both free and regulated customers.
COES warns southern region will need a third 500 kV line for nighttime operations
Nevertheless, the Economic Operation Committee of the National Interconnected System (COES) maintains that the renewable energy expansion will necessitate new infrastructure and backup capacity to ensure system security.
César Butrón, the committee’s president, noted that the concentration of solar parks in the south has led COES to propose a third 500 kV transmission line connecting the central and southern regions. This line is intended to meet the area’s nighttime demand, a period when photovoltaic plants cease generation.
Butrón explained that by 2036, solar production could reverse the direction of power flows at midday, enabling electricity to be transmitted from the south to the center. At night, the flow would reverse again, as the southern region would require power imports from the central grid.
The situation could worsen if the Southern Mining Corridor expands, given that its demand operates around the clock. The head of the COES cited instances where effective solar generation in the south fell up to 400 MW below forecasts at midday due to cloud cover, in a region that hosts approximately 1,000 MW of installed photovoltaic capacity.
The COES president added that during the dry season, hydroelectric generation can drop by roughly 1,000 MW compared to the rainy season, while wind output in the described scenario declined by 300 MW. He noted that if gas plants are already running at full capacity, the system may need to rely on diesel generation.
He also estimated that Law No. 32249, which underpins the disputed regulation, would cover only 40% of demand, while the remaining 55% corresponds to free-market customers who typically sign contracts for three to five years—terms that do not facilitate financing for new firm generation.
Pvola take
Excluding new renewables from long-term tenders removes the revenue certainty required for bank financing. Developers cannot secure debt for 14.5 GW of projects if they must compete with legacy plants for short-term contracts. This regulatory gap stalls investment in high-potential regions like Ica and Arequipa.
Frequently asked questions
Why did the Peruvian renewable energy sector warn of an investment slowdown regarding the new MINEM regulation?
The regulation omits long-term tenders of up to 15 years for new wind and solar projects. This omission prevents developers from securing the long-term contracts required to obtain bank financing for new projects.
What is the current installed photovoltaic capacity in Peru and what is the planned expansion in the Ica region?
Peru has surpassed 1,200 MW of installed photovoltaic capacity as of August 2026. Eleven additional solar projects in Ica, Arequipa, and Moquegua are planned to add 2,000 MW of capacity.
How does the lack of long-term tenders affect the financial viability of new solar and wind projects in Peru?
Without long-term contracts, new projects cannot compete with operational plants for the agreements needed to secure bank financing. This creates a barrier to investment and may force the grid to rely on diesel generators for backup power.