Waroona 132 MW Solar and Battery Construction Begins in Australia

3 min read
Waroona 132 MW Solar and Battery Construction Begins in Australia

The short answer

Frontier Energy has commenced major construction on the 132 MW solar and 81.5 MW battery Stage One of the Waroona project in Western Australia. The facility is designed to connect to the SWIS via the 330 kV Landwehr Terminal, offsetting one-third of the retiring Collie coal station's output.

Key facts

Capacity
132 MW solar and 81.5 MW/6.9-hour battery storage for Stage One
Stage
Stage One, with Stage Two approval secured for 120 MW solar and 80 MW storage
EPC or contractor
Monford Group holds the fixed-price EPC contract for Stage One
Grid connection
Connects to SWIS via adjacent 330 kV Landwehr Terminal
Owner or developer
Frontier Energy
COD
Expected to begin generating power in 2028
Location
Approximately 120 km south of Perth, Western Australia

Frontier Energy, an Australian developer, announced that major construction has begun on Stage One of its Waroona Renewable Energy Project in southwest Western Australia. The company expects the first stage to begin generating power in 2028.

Situated approximately 120 kilometres south of Perth, the state capital, the initial phase includes a 132 MW solar array and an 81.5 MW/6.9-hour battery energy storage system. This DC-coupled infrastructure is engineered to store solar energy generated during daylight hours and release it into the grid when demand peaks.

Adam Kiley, Chief Executive Officer of Frontier Energy, stated that the project will connect to the South West Interconnected System (SWIS), Western Australia’s primary electricity network, through the adjacent 330 kV Landwehr Terminal. He noted that the first stage is projected to offset one-third of the electricity currently produced by the Collie coal-fired power station, which is scheduled to shut down in 2027.

“Once energy generation begins in 2028, the Waroona project will stand as the largest solar and battery hybrid facility connected to Western Australia’s main electricity network, playing a pivotal role in helping the state achieve its goal of 75% renewable energy by 2031,” the executive stated, noting that the company plans to evolve Waroona into a multi-stage renewable energy hub.

“Stage One marks just the initial phase for Frontier, as we are committed to expanding beyond this first stage to position the Waroona project as a significant renewable energy hub in the heart of southwest Western Australia,” he continued. “This development will introduce much-needed new generation capacity to the grid in a region that has relied on coal-fired power for over six decades.”

Looking past the initial phase, Frontier aims to significantly scale up the development. The company’s long-term strategy targets the installation of approximately 1 gigawatt of solar generation capacity and 660 megawatts of battery storage by 2031.

Development approval has already been secured for Stage Two, which outlines the construction of approximately 120 megawatts of solar generation facilities alongside 80 megawatts of battery storage.

Monford Group, a Western Australian contractor, has secured the fixed-price engineering, procurement and construction (EPC) contract for the initial phase of the Waroona project. The firm is tasked with the construction and commissioning of the integrated solar and battery facility.

Longi, a Chinese manufacturer, has been selected to supply the solar modules, while Trina Storage will provide the battery system. Nextpower is set to furnish the solar tracking equipment, and SMA Australia will supply the inverters.

Key construction activities will involve field piling to support the single access tracking system, followed by the installation of photovoltaic modules and the construction of the solar facility’s balance of plant. These works are scheduled to begin in early 2027.

The commencement of construction on the Waroona project follows Frontier’s execution, earlier this month, of a syndicated facility agreement for project finance debt facilities of up to AUD 280 million ($194 million). The syndicate of international lenders is led by France-headquartered investment bank Natixis CIB and Japanese financial services conglomerate Sumitomo Mitsui Banking Corporation.

Frontier Energy has finalized its Capacity Investment Scheme agreement with the Australian government, securing a guaranteed minimum revenue stream for the project through 2042.

The company has also received capacity credits for the first stage of the Waroona project under the Australian Energy Market Operator’s Reserve Capacity Mechanism. This five-year fixed contract provides the project with approximately AUD 160 million in revenue certainty.

Pvola take

This project signals a critical shift in Western Australia's grid as it replaces retiring coal capacity with firmable renewable energy. The secured revenue mechanisms, including the Capacity Investment Scheme and Reserve Capacity Mechanism, de-risk the asset for investors. Frontier's long-term 1 GW target demonstrates a scalable model for regional energy hubs.

Frequently asked questions

When is the first stage of the Waroona Renewable Energy Project expected to begin generating power?

The first stage of the Waroona project is expected to begin generating power in 2028. This initial phase includes a 132 MW solar array and an 81.5 MW/6.9-hour battery energy storage system.

How much revenue certainty does the Waroona project receive under the Reserve Capacity Mechanism?

The project receives approximately AUD 160 million in revenue certainty through a five-year fixed contract. This contract provides a guaranteed minimum revenue stream for the project through 2042.

What is the long-term capacity target for the Waroona project by 2031?

Frontier Energy targets the installation of approximately 1 gigawatt of solar generation capacity and 660 megawatts of battery storage by 2031. Development approval has already been secured for Stage Two, which outlines the construction of approximately 120 megawatts of solar generation.