PvolaSolar & Storage← All stories

Policy Desk

Analysts push back on solar blank by T&TEC: No batteries needed

Trinidad Guardian14 min read
Analysts push back on solar blank by T&TEC: No batteries needed

The Gov­ern­ment’s de­ci­sion to halt elec­tric­i­ty from flow­ing on­to the na­tion­al grid from T&T’s largest so­lar farm has ig­nit­ed fierce crit­i­cism from for­mer min­is­ters, en­er­gy ex­perts and re­new­able en­er­gy ad­vo­cates, all warn­ing the coun­try risks un­der­min­ing its en­er­gy tran­si­tion and wast­ing an in­vest­ment that was ex­pect­ed to trans­form the elec­tric­i­ty sec­tor.

This af­ter Pub­lic Util­i­ties Min­is­ter Bar­ry Padarath con­firmed to Busi­ness Guardian last week Thurs­day that the Trinidad and To­ba­go Elec­tric­i­ty Com­mis­sion (T&TEC) is no longer ab­sorb­ing elec­tric­i­ty gen­er­at­ed by the 92-megawatt Brechin Cas­tle So­lar Ltd (BC­SL) fa­cil­i­ty, the coun­try’s first util­i­ty-scale so­lar farm. He dis­closed that the plant stopped feed­ing the grid at the end of Jan­u­ary and blamed short­com­ings in plan­ning and con­trac­tu­al arrange­ments un­der the for­mer ad­min­is­tra­tion.

The Brechin Cas­tle fa­cil­i­ty, joint­ly owned by Shell (35 per cent), bpTT (35 per cent) and the Na­tion­al Gas Com­pa­ny (30 per cent), was ex­pect­ed to sup­ply about eight per cent of Trinidad and To­ba­go’s elec­tric­i­ty de­mand while free­ing up nat­ur­al gas for ex­port and high­er-val­ue down­stream in­dus­tries.

The project rep­re­sent­ed the coun­try’s biggest re­new­able en­er­gy in­vest­ment and, once ful­ly com­mis­sioned, was ex­pect­ed to be­come the largest util­i­ty-scale so­lar farm in the Caribbean.

For­mer en­er­gy min­is­ter Stu­art Young dis­missed the Gov­ern­ment’s han­dling of the is­sue as a ma­jor pol­i­cy fail­ure, ar­gu­ing that of­fi­cials had ig­nored the project’s broad­er eco­nom­ic val­ue.

“It is very dis­ap­point­ing to see the Gov­ern­ment take such a back­ward step. This project was sig­nif­i­cant on many fronts for Trinidad and To­ba­go and was done in col­lab­o­ra­tion with both bp and Shell.”

Young main­tained that the project’s eco­nom­ics ex­tend­ed well be­yond elec­tric­i­ty gen­er­a­tion.

“The cost of the project and a kilo­watt of elec­tric­i­ty was glob­al­ly com­pet­i­tive. A ma­jor ben­e­fit was the sav­ing of mol­e­cules of nat­ur­al gas away from loss-mak­ing pow­er gen­er­a­tion and the avail­abil­i­ty of NGC tak­ing that nat­ur­al gas and sell­ing it to com­mer­cial cus­tomers in the petro­chem­i­cal sec­tor or us­ing it in LNG.”

He ar­gued that bat­tery stor­age was nev­er in­tend­ed to form part of the de­sign be­cause elec­tric­i­ty gen­er­at­ed dur­ing day­light hours was ex­pect­ed to flow di­rect­ly on­to the na­tion­al grid.

“There was no bat­tery stor­age be­cause all of the pow­er gen­er­at­ed was to be im­me­di­ate­ly ab­sorbed in­to our na­tion­al elec­tric­i­ty grid. Bat­tery stor­age is not on­ly ex­pen­sive but it was un­nec­es­sary as the dri­ver was pro­duc­ing elec­tric­i­ty via a re­new­able source, there­by sav­ing nat­ur­al gas which would have been used in elec­tric­i­ty gen­er­a­tion and sell­ing those mol­e­cules of gas for sig­nif­i­cant­ly more.”

Young added that the project al­so cre­at­ed op­por­tu­ni­ties be­yond elec­tric­i­ty pro­duc­tion.

“Ad­di­tion­al­ly, this project earned car­bon cred­its and pro­duced 8 per cent of our elec­tric­i­ty needs via clean, green re­new­able means. This scale of so­lar pow­er plant can al­so con­tribute sig­nif­i­cant­ly to huge projects that re­quire large amounts of elec­tric­i­ty, as it was set to gen­er­ate 92 MWs.”

He point­ed to emerg­ing in­dus­tries re­quir­ing mas­sive elec­tric­i­ty sup­plies.

“You would see the AI Hy­per­scale Da­ta Cen­ters be­ing pro­posed to use over 100 MWs. We were al­so ex­plor­ing the use of so­lar pow­er gen­er­at­ed be­ing used in Green Hy­dro­gen pro­duc­tion.”

Young con­clud­ed that, “It is very dis­turb­ing how the un­in­formed de­ci­sions be­ing made by the UNC are set­ting T&T back decades.”

The for­mer ad­min­is­tra­tion had al­so ad­vanced plans for an­oth­er large re­new­able en­er­gy project at Or­ange Grove. That de­vel­op­ment, led by Light­source bp on be­half of bp Al­ter­na­tive En­er­gy T&T and Shell Re­new­ables Caribbean Ltd, was lat­er shelved af­ter Cab­i­net de­cid­ed to use the land for an­oth­er pur­pose.

For­mer pub­lic util­i­ties min­is­ter Mar­vin Gon­za­les al­so crit­i­cised the Gov­ern­ment’s po­si­tion, ar­gu­ing that re­new­able gen­er­a­tion would have re­duced pres­sure on both tax­pay­ers and the coun­try’s gas sup­plies.

“The re­cent re­port I read con­firms that this is a back­ward step by the Gov­ern­ment. The so­lar farm was meant to tran­si­tion our elec­tric­i­ty gen­er­a­tion in­to a more re­silient and mod­ern eco-friend­ly sys­tem with less de­pen­dence on fos­sil fu­els.”

He con­tend­ed that di­vert­ing less gas in­to elec­tric­i­ty gen­er­a­tion would have ben­e­fit­ed the wider econ­o­my.

“More gas would have be­come avail­able to sup­port our en­er­gy in­dus­try and earn much more scarce for­eign ex­change.”

Gon­za­les added that low­er gas con­sump­tion by T&TEC would al­so have re­duced the bur­den cre­at­ed by elec­tric­i­ty sub­si­dies.

“The ris­ing debt owed to NGC by T&TEC as a re­sult of the gas sub­sidy would have been lim­it­ed in the com­ing years as less gas would have been need­ed to gen­er­ate elec­tric­i­ty. This would have saved tax­pay­ers bil­lions in the next decade.”

He al­so de­fend­ed the ab­sence of bat­tery stor­age.

“Bat­tery stor­age would have made the project very ex­pen­sive, and the tech­ni­cal ad­vice was that it was not need­ed giv­en the fact that the elec­tric­i­ty gen­er­at­ed was to be im­me­di­ate­ly placed on the na­tion­al grid.”

Gon­za­les ar­gued that re­new­able elec­tric­i­ty would al­so have sup­port­ed fu­ture green hy­dro­gen pro­duc­tion while help­ing Trinidad and To­ba­go re­duce green­house gas emis­sions.

“It is just po­lit­i­cal spite and nar­row-mind­ed­ness that in­flu­enced this pol­i­cy shift by the Gov­ern­ment, and yet again, they have placed Trinidad and To­ba­go at the back of the class.”

One source told the Busi­ness Guardian that in­cor­po­rat­ing bat­ter­ies in­to a so­lar fa­cil­i­ty of that size would have in­creased cap­i­tal ex­pen­di­ture by be­tween 70 and 100 per cent, mak­ing the project sig­nif­i­cant­ly less at­trac­tive com­mer­cial­ly. The source added that the 92-megawatt out­put dur­ing day­light hours was ex­pect­ed to be bal­anced by re­duc­ing gen­er­a­tion from ex­ist­ing gas-fired pow­er sta­tions, al­low­ing nat­ur­al gas sav­ings with­out the need for ex­pen­sive bat­tery sys­tems.

With elec­tric­i­ty no longer flow­ing from the coun­try’s flag­ship so­lar fa­cil­i­ty, at­ten­tion is now turn­ing to whether tech­ni­cal up­grades, bat­tery stor­age and long-term grid mod­erni­sa­tion can re­vive a project once pro­mot­ed as the cen­tre­piece of Trinidad and To­ba­go’s re­new­able en­er­gy fu­ture.

En­er­gy sec­tor ex­pert Dr Thack­wray Dri­ver de­scribed the sit­u­a­tion as deeply dis­ap­point­ing but cau­tioned that the dif­fi­cul­ties point to broad­er weak­ness­es with­in the coun­try’s elec­tric­i­ty sys­tem rather than flaws in re­new­able en­er­gy it­self.

“As some­one who has long ad­vo­cat­ed for more re­new­able en­er­gy in Trinidad & To­ba­go, the news that the biggest so­lar project in the Eng­lish-speak­ing Caribbean was un­able to dis­patch elec­tric­i­ty to the grid comes as a big dis­ap­point­ment.”

Dri­ver ex­plained that main­tain­ing grid sta­bil­i­ty ap­pears to have be­come the prin­ci­pal ob­sta­cle.

“What has be­come clear is that T&TEC has faced sig­nif­i­cant grid man­age­ment prob­lems with ac­cept­ing the in­ter­mit­tent elec­tric­i­ty on­to the grid.”

He not­ed that sys­tem op­er­a­tors re­port­ed­ly had to in­crease spin­ning re­serves from gas-fired gen­er­a­tors to ac­com­mo­date fluc­tu­at­ing so­lar gen­er­a­tion.

“Ac­cord­ing to in­dus­try sources, the vol­ume of gas re­quired to keep this spin­ning re­serve avail­able from these pow­er sta­tions is sur­pris­ing­ly even more than the sav­ings in gas from the im­ple­men­ta­tion of the so­lar project.”

Dri­ver ob­served that T&TEC had pre­vi­ous­ly in­di­cat­ed the grid could com­fort­ably ac­com­mo­date the so­lar elec­tric­i­ty.

“While T&TEC pre­vi­ous­ly pub­licly and re­peat­ed­ly stat­ed that they could eas­i­ly ab­sorb the in­ter­mit­tent so­lar from the project on­to the grid, this ap­par­ent­ly turned out not to be the case when the elec­tric­i­ty ac­tu­al­ly be­gan to flow.”

He be­lieves age­ing gen­er­at­ing equip­ment and changes to con­trol sys­tems com­pli­cat­ed op­er­a­tions.

“The im­me­di­ate so­lu­tion to this prob­lem is the in­stal­la­tion of bat­ter­ies on the grid to smooth the flow of the elec­tric­i­ty from the so­lar plant on­to the grid and en­able grid sta­bil­i­ty with­out the need for an in­creased nat­ur­al gas-fired spin­ning re­serve.”

Dri­ver wel­comed the In­ter-Amer­i­can De­vel­op­ment Bank’s move to seek con­sul­tants for an In­te­grat­ed Re­source and Re­silience Plan to mod­ernise the coun­try’s elec­tric­i­ty net­work over the next two decades, say­ing the ex­er­cise was over­due.

He al­so point­ed to glob­al changes in elec­tric­i­ty mar­kets.

“The boom in AI da­ta cen­tres, es­pe­cial­ly in the USA, has put a strain on the tur­bine man­u­fac­tur­ing sup­ply chain and with de­mand out­strip­ping sup­ply, prices are re­port­ed to have more than dou­bled in the past few years.”

That trend, he ar­gued, has made re­new­able pow­er in­creas­ing­ly com­pet­i­tive com­pared with new gas-fired gen­er­a­tion.

Dri­ver stressed that the Brechin Cas­tle ex­pe­ri­ence should not de­rail the coun­try’s re­new­able am­bi­tions.

“Clear­ly lessons need to be learnt from this ex­pe­ri­ence, but it must not be used to un­der­mine the over­all push to in­crease re­new­able en­er­gy pen­e­tra­tion and to re­duce the vol­ume of nat­ur­al gas be­ing used to gen­er­ate elec­tric­i­ty.”

Eco­nom­ic ac­tivist Dr Wayne Kublals­ingh al­so de­scribed the project’s sus­pen­sion as a ma­jor set­back, fram­ing the is­sue as an eco­nom­ic rather than en­vi­ron­men­tal one.

“I think this is a very trag­ic sit­u­a­tion that we have shut down this project. I think every­body would agree with that.”

He ar­gued Trinidad and To­ba­go should go much fur­ther by es­tab­lish­ing an in­dus­tri­al es­tate ded­i­cat­ed to man­u­fac­tur­ing re­new­able en­er­gy com­po­nents.

“I think we need to de­vel­op an in­dus­tri­al es­tate sole­ly de­vot­ed to mak­ing com­po­nents for the so­lar and re­new­able in­dus­tries in Trinidad and To­ba­go and the Caribbean.”

Kublals­ingh sug­gest­ed the coun­try could part­ner with in­ter­na­tion­al man­u­fac­tur­ers to pro­duce so­lar pan­els, bat­ter­ies, in­vert­ers and oth­er equip­ment lo­cal­ly.

He al­so pro­posed large-scale de­vel­op­ment of so­lar-pow­ered smart homes to re­duce house­hold liv­ing costs while cre­at­ing de­mand for lo­cal­ly man­u­fac­tured prod­ucts.

“The best eco­nom­ic op­tion for Trinidad and To­ba­go is to in­vest in these, not just a so­lar farm, but an in­dus­tri­al es­tate to­tal­ly de­vot­ed to the pro­duc­tion of com­po­nents.”

He main­tained that en­er­gy se­cu­ri­ty has be­come in­creas­ing­ly im­por­tant as geopo­lit­i­cal ten­sions re­shape glob­al en­er­gy mar­kets.

“We have to go full-scale with so­lar and re­new­able in­dus­tries. And not just in­dus­tries, but the tech­nolo­gies. We have to cre­ate our own tech­nol­o­gy.”

In­dus­try sources fa­mil­iar with the Brechin Cas­tle project al­so de­fend­ed the orig­i­nal de­sign, ex­plain­ing that adding bat­tery stor­age would have dra­mat­i­cal­ly in­creased con­struc­tion costs.

Want FREE access to all our content? Sign up HERE!

Frequently asked questions

Why are energy experts criticizing the government's decision to halt power from the Brechin Castle Solar facility?

Critics argue the move undermines the country's energy transition and wastes a significant investment. They contend that the policy shift is driven by political spite rather than technical necessity, placing the nation at a competitive disadvantage in renewable energy development.

What is the capacity of the Brechin Castle Solar facility and what was its expected contribution to national electricity demand?

The 92-megawatt facility was designed to supply approximately eight percent of Trinidad and Tobago's electricity demand. It was intended to free up natural gas for other uses and support future green hydrogen production while reducing greenhouse gas emissions.

Why did industry sources argue that adding battery storage to the Brechin Castle project was not a viable solution?

Industry sources stated that adding battery storage would have dramatically increased construction costs for the project. They defended the original design, suggesting that the current operational issues stem from planning and contractual shortcomings rather than a lack of storage technology.